PROJECT SCHEDULE

SUGAR CREEK OVERALL PROJECT SCHEDULE

The project construction period began April 1, 2019. 

Installation of underground collection lines began in November 2019 and was completed in May 2020. 

During the Spring of 2020, cranes and wind turbine components began to arrive with Turbine installation beginning in May 2020 and completed at the end of September 2020.   Project commercial operations began on November 9, 2020.